The engineer is working on revised blueprints and we should have the new documents by April 20.
They are going to level the lot by April 15, which means it will be ready for staking the house when Lisle is there on May 3.
Probably means we are behind schedule by 90 days since they can't make permit application until the drawings are complete and that won't be until Lisle returns them at the beginning of May.
Oh well - what would a project be without delays - just need to maintain the forward momentum!